LP
CONSTRUCTION LOOKAHEAD PLANNER
Piping Scope & Scheduling
Loading…
No Project
🗺 Build Phases
📂 Quick Actions
🏗 Project Identity
Project Type
📋 Client & Contract
📅 Calendar & Work Schedule
📅 Project Holidays
Dates are generated for every year the project spans. Fixed and calculated holidays (Easter, "4th Thursday of November") are exact; Islamic dates are estimates until confirmed. Holidays you add yourself are kept when you switch region.
DateDayHolidayCategory
📐 Estimating Defaults
100% = no adjustment
💾 Data Management
🔧 Piping Systems
CodeDescriptionFluidTemp MaterialScheduleJoining / FittingsInsul.Press.HangerCategoryNotes
📐 Support Spacing Calculator

Calculate adjusted pipe support spacing per ASME B31.3 / MSS SP-69. Factors: temperature, insulation weight, fluid density, wall thickness.

📎 Hanger Types Reference
CodeDescriptionApplicationMH/ea
📏 Project Pipe Sizes

Select which pipe sizes are used on this project.

⚙ Production Rates
💡 Output per crew per productive hour · Weld Inches = Diameter × No. of Welds · LF = linear feet installed · Double-click a row to edit a rate
Duration = crew-hours ÷ productive hrs/day. Adding people to one crew prices the work higher but does not shorten it — run more crews for that. Nominal crew:
Material Type Weld-in per hr Linear Ft per hr Hangers per hr Source
🚦 Start-up & Priority
LEAD TIMES working days
📋 Reports
🔢 CWA Number Format

Structure: PREFIX-BUILDING-FLOOR-AREA-DISCIPLINE-RUNNING

Preview:
🏗 CWA Directory
💡 Click ▸ to see the work packages inside a CWA · Blue quantities are rolled up from ISOs assigned in the ITL · grey are planning-scope estimates · crew-hrs needed = quantities ÷ production rates (field welds only); supplied = duration × productive hrs for one crew — the badge flags a gap over 10%
CWA NumberDescriptionDisciplineBuildingFloorArea SpecStatusStartFinish ISOsLF WIHgr
⚙ Resource Calculator — All CWAs
CWAMaterialWork DaysTotal MH CrewsWeldersFittersHelpersTotal Craft ForemenTotal WorkersLabour CostConstraining
📊 Manpower Curve
🔧 Project Equipment List
Project weeks
💡 Quantities are derived from crew and welder counts — double-click a row to override or add a note · ✱ = manual override · Items whose material condition isn't met show greyed with qty 0
LIST
Items on project:0
Active (qty > 0):0
Not applicable:0
RESOURCE DRIVERS
Welders:0
Crews:0
Foremen:0
COST
Hire:0
Purchase:0
TOTAL
Equipment cost:0
🔍
ItemUnitBasisQty SourceCondition Hire/WkPurchase Hire CostPurch Cost Total
📚 Equipment Library Master catalogue — shared across all projects
💡 Double-click to edit rates or basis — changes apply to every project using this library · Greyed rows don't match this project's materials
CATALOGUE
Library items:0
Applicable here:0
On this project:0
Your own additions:0
🔍
ItemDescriptionUnitBasisSource ConditionHire/WkPurchase
📉 Equipment Release Schedule When to off-hire as crews demobilise
Ramp-up wks Ramp-down wks
💡 Only hired, crew-scaled items appear — consumables and per-project items are held for the full duration. Saving assumes each step is returned on schedule.
📊 Cost Summary Equipment · Labour · Combined
🔧 Equipment Cost by Category
👷 Labour Cost
💰 Combined Summary
Project Personnel Roster
Viewing as:
💡 Double-click any row to edit details, set assignment dates and view cost breakdown · Amber row = approaching end date · Red row = overdue
CRAFT LABOR
Estimated:$0
Budgeted:$0
Actual:$0
Variance (Est−Bud):$0
Remaining (Est−Act):$0
ENG / MANAGEMENT
Estimated:$0
Budgeted:$0
Actual:$0
Variance (Est−Bud):$0
Remaining (Est−Act):$0
PROJECT TOTAL
Estimated:$0
Budgeted:$0
Actual:$0
Variance (Est−Bud):$0
Remaining (Est−Act):$0
🔍 Category: Status:
NameCategoryRoleGrade Plan StartPlan FinishAct. StartAct. Finish Personal RateProject RateCommit %Travel/Day Budgeted CostActual Cost
Select a crew from the list or click + New Crew to get started
Visual crew organisation — Superintendent → Foremen → Crews → Workers
💵 Labour Rate Sheet
💡 Rates provided by Estimating Dept · Import CSV or edit manually · Auto-fills Project Rate when workers are assigned in the Roster · Red row = $0.00 rate not yet set
COVERAGE
Roles defined:0
Rates set:0
Missing ($0.00):0
CRAFT RATES
Lowest:—
Average:—
Highest:—
STAFF / NON-CRAFT RATES
Lowest:—
Average:—
Highest:—
ROSTER MATCH
Workers on roster:0
Matched to a rate:0
No matching rate:0
🔍 Category: Grade:
Role Category Grade Rate/hr OT Mult. OT Rate/hr Effective Notes On Roster
📋 Item Tracking Log (ITL)
📦 Fab Delivery Day:
VIEW:
CWA: Material: Status: Search:
📝 Task Management
0 tasks 0 not started 0 in progress 0 complete 0 MH
Crew: Status: CWA: Search:
📊 Lookahead Gantt Chart from: to: Show at most: Zoom: Day
◼ Not Started ◼ In Progress ◼ Complete ◼ Delayed ◼ On Hold ▬ Baseline (original dates) | Today Weekend Holiday
🤖 Project Assistant